Pending is not approved: reporting change exposure to the owner
The cost report counts executed change orders. The exposure lives in the pending list, the handshake, and the unpriced RFI. That is the number to take upstairs.
First shared on LinkedIn on October 8, 2026. Read the original post.
Your contingency balance is not what is left. It is what is left before the pending changes.
Say the cost report shows $412,000 of owner contingency remaining. Everyone at the OAC relaxes. Then you open the other logs. Two pending changes for added fire dampers. A handshake on rerouting a storm line around an old footing. An RFI response that moved the rooftop units and has not been priced. Put a rough number on each and the real balance is closer to $150,000. The roof, the elevator, and the finishes are still in front of you.
Nobody hid anything. The report did its job. It counted what is executed. It did not count what is already in motion.
Pending is not approved
A pending PCO is a claim, not a decision. A handshake is not a PCO. "Proceed pending PCO" is not a change order. An answered RFI with cost impact and no price is not a zero.
I have seen this play out the same way more than once. A Friday email says proceed on the extra duct run and paper it next week. Crews show Monday. The work gets built. Three weeks later the duct is in, the PCO still is not issued, and the pay app has a line for it. Finance rejects it because there is no signed change. The GC is carrying the labor and the material. Or the cost gets buried in contingency so the report still looks clean. Either way, the owner's number is wrong.
That email is a field directive. It is not a PCO number, dollars, days, or a signature. Until those four exist, the change is not on the books. It is still exposure.
The four numbers I take upstairs
I start every Monday with one page. Four numbers. No narrative.
- Contingency per the report. The executed balance. This is the number everyone already has.
- Pending PCOs at submitted value. What is already written and not signed. Use the GC's number, not a guess.
- Unpriced RFIs and handshakes, at your own rough estimate. If there is no number, you put one on in pencil that day. "TBD" is not a number.
- What is left after all three. That last number is the one I take upstairs. Not the first one.
If you cannot fill the third line because nobody has estimated the work, that is the finding. The gap is the point of the page.
Dollars and days
Exposure is not only money. "Days: TBD" is the most expensive line on a change, because the work starts and the time impact gets argued after the duration is already gone. If a pending change has a dollar number and no days, the days are still pending. Put a rough duration on the page next to the money, even if it is your number in pencil, and mark it as an estimate.
Do not net the pending list down because someone said they will value-engineer it later. A hoped-for savings is not an executed credit. Leave the exposure on the page until a signed change takes it off.
When you have to pencil an unpriced item, write the basis in a few words: similar change on this job, a vendor email, or a unit price times a quantity you can see. The point is not to be exact. The point is to stop treating a blank as zero when you talk to the owner.
Monday move
Build the page before the cost report goes out. Then clean the source list so next Monday is shorter.
- Pull the last 30 days. Every "proceed pending," "start now," and "we'll paper it later" note from email and OAC minutes.
- Match each one to a PCO number. Anything without a number gets a draft PCO by Friday: dollars, days, and a needed-by signature date.
- One name owns the list. Bring the open ones to the OAC. If a change is already in the field with no paper, say that out loud.
The owner does not need a cleaner cost report. The owner needs the real balance while there is still time to choose.
Sent to your inbox. Unsubscribe anytime. PDF and Excel: agenda, action register, decision log, and RFI tracker.
More core ideas
- How to run the weekly owner's meetingRead
- What you can still do when the AI policy says noRead
- Pending is not approved: reporting change exposure to the ownerRead
- The three-question weekly owner's reportRead
- Why every action needs a name and a dateRead
- Sorting submittals by need-on-site dateRead
- Long-lead items and the last responsible release dateRead
- Decision logs: what was decided, and when it was neededRead